Task 6

SHORE PROJECT Task 6:
S.H.O.R.E. Project ? Shoreline Restoration

9/30/2010 All shorelines have been completed. We added two new locations this summer and restored them in July. All residents who were willing to become involved in the program were helped. Conservation has been notified to release the Order of Conditions and issue a Certificate of Compliance for all properties.
9/30/2008 10 of 14 sites completed, 400 ft of shoreline planted
6/30/2008 12 sites mapped & designs created, project NOI approved
3/31/2008 20 homeowners contacted, site visits
12/31/2007 New wall built at 1st site, sample coir logs installed
9/30/2007 Native species chosen, identified restoration site homeowners contacted, 1st restoration begun
LLsite May 2005

LLsite May 2005

LLsite Sept 2007

LLsite Sept 2007

LLsite July 2008

LLsite July 2008

LLsite Aug 2008

LLsite Aug 2008

“This project has been financed with Federal Funds from the Environmental Protection Agency (EPA) to the Massachusetts Department of Environmental Protection (the Department) under an s. 319 competitive grant. The contents do not necessarily reflect the views and policies of EPA or of the Department, nor does the mention of trade names or commercial products constitute endorsement or recommendation for use.”