Home>Environment>Current Project
Task 3:
Creation of No Wake Zones and Noxious Aquatic Harvesting
| 9/30/2008 |
No Wake signs placed at restoration sites & boat ramp |
| 6/30/2008 |
No additional work was performed on this task |
| 3/31/2008 |
Plant survey results--no harvesting needed currently |
| 12/31/2007 |
Noxious plant survey by Dr. Jon Lyon |
| 9/30/2007 |
Shorline survey Nov 2006, buoy sites identified |

No Wake sign at restoration site, Aug 2008
"This project has been financed with Federal Funds from the Environmental Protection Agency (EPA) to the Massachusetts Department of Environmental Protection (the Department) under an s. 319 competitive grant. The contents do not necessarily reflect the views and policies of EPA or of the Department, nor does the mention of trade names or commercial products constitute endorsement or recommendation for use."
Back
to Top