Task 6:
S.H.O.R.E. Project – Shoreline Restoration
Click here for more Before and After pictures
| 9/30/2008 |
10 of 14 sites completed, 400 ft of shoreline planted |
| 6/30/2008 |
12 sites mapped & designs created, project NOI approved |
| 3/31/2008 |
20 homeowners contacted, site visits |
| 12/31/2007 |
New wall built at 1st site, sample coir logs installed |
| 9/30/2007 |
Native species chosen, identified restoration site homeowners contacted, 1st restoration begun |

LLsite May 2005

LLsite Sept 2007

LLsite July 2008

LLsite Aug 2008
"This project has been financed with Federal Funds from the Environmental Protection Agency (EPA) to the Massachusetts Department of Environmental Protection (the Department) under an s. 319 competitive grant. The contents do not necessarily reflect the views and policies of EPA or of the Department, nor does the mention of trade names or commercial products constitute endorsement or recommendation for use."